Why Photometric Plans Get Rejected at Plan Review (and How to Fix Them)

Point-by-point photometric plan grid with foot-candle values around two buildings and wall-mounted fixtures

Most photometric plans don’t get rejected because the lighting is bad. They get rejected because the plan doesn’t prove the lighting meets the local code. The usual reasons are a missing point-by-point grid, no light levels at the property line, only an average foot-candle value instead of max/min/avg and uniformity, a fixture schedule that doesn’t match the cut sheets and IES files, and missing mounting heights or shielding details.

The good news: almost every comment can be fixed in a revision. Below are the most common ones, what the reviewer is asking for, and how to fix each.

Got a correction letter? Send us your plan and the reviewer’s comments. We’ll tell you what needs to change, with no payment required to get a quote.

1. The Point-by-Point Grid Is Missing or Incomplete

A heat map alone is not enough for most reviewers. Many U.S. zoning codes ask for foot-candle values on a regular grid across the entire site, and often past the property line too. For example, Bloomington, MN asks for points on a grid of 10 ft x 10 ft or less across the entire site and at least 10 ft beyond the property line, with each value to the nearest 0.1 foot-candle (fc). Scottsdale, AZ uses a similar 10 ft maximum spacing.

Common comments in this group:

  • “Provide point-by-point foot-candle values for the entire site.”
  • “Extend the calculation grid 10 feet beyond the property line.”

How to fix it: Rerun the calculation with one grid that covers the whole site, using the spacing your code requires (10 ft is common, and some jurisdictions ask for less). Extend it past the property line by the distance the code requires. Show values to one decimal place and mask out only the building footprints. If you’re not sure how to read the numbers on your own plan, see our guide on how to read a photometric plan.

Point-by-point photometric plan grid with foot-candle values around two buildings and wall-mounted fixtures
A point-by-point grid shows a calculated foot-candle value at every point, so the reviewer can check minimums and spill without guessing.

2. Light Trespass at the Property Line

This is one of the most common reasons exterior lighting plans come back. Many codes cap how much light can cross the property line, especially next to homes or a public road. The limit varies a lot:

  • Madison, WI: light trespass cannot exceed 0.5 fc at 10 ft past the property line.
  • Loudoun County, VA: no more than 0.25 fc above background light levels at the lot line of an adjacent lot or road right-of-way.

Some jurisdictions also want a vertical light trespass check. Scottsdale, for example, asks for vertical readings 6 ft above grade along the entire property line.

How to fix it: Label the property line clearly on the plan and show the values at and beyond it. If the numbers are too high, the usual fixes are a different optic (for example, a Type III or IV forward-throw distribution instead of Type V), a house-side shield, a lower mounting height, or moving the pole further from the line. Add a calculation summary row just for the property line so the reviewer doesn’t have to hunt for it. Sign lighting gets the same comments; see our signage photometric plan guide.

Photometric plan foot-candle grid extending past the labeled outer property line
The calculation grid continues past the labeled property line, where most values read 0.0 fc.

3. Only an Average Is Shown (No Max/Min or Uniformity)

A plan can show a healthy average and still fail. Reviewers usually look at the minimum and the uniformity ratio, because those reveal dark spots between poles. Many codes ask for maximum, minimum, and average foot-candles plus max/min and/or avg/min uniformity for each use area, such as parking, drive aisles, and pedestrian areas.

How to fix it: Add a calculation summary table with separate zones for each area the code regulates. List average, max, min, max/min, and avg/min for each. Then compare those values directly to the code’s numbers. If a zone fails, it’s usually a spacing or optic issue, not a wattage issue. Adding light to raise the minimum often pushes the maximum and the trespass values up too. For typical target levels by area, see our foot-candle requirements by area guide.

False-color heat map of a courtyard lighting design with a foot-candle scale from 0 to 5
A false-color view makes uneven areas easy to spot, but reviewers still expect the numeric min, max, average, and uniformity in a summary table.

4. Fixture Schedule, Cut Sheets, and IES Files Don’t Match

Reviewers check that what you calculated is what you’ll install. Common comments:

  • “Provide manufacturer cut sheets for all fixtures.”
  • “Fixture tags on the plan do not match the schedule.”
  • “Provide lumens, CCT, and wattage for each fixture.”

This often happens when fixtures are swapped late and the calculation isn’t rerun.

How to fix it: Make the plan tags, the fixture schedule, and the cut sheets use the same labels (Type A, Type B, and so on). On each cut sheet, mark the exact catalog number, optic, lumen package, and CCT you’re using. Make sure the IES file in the calculation is for that exact configuration. If the fixture changed, rerun the calculation. Don’t just edit the schedule.

5. Mounting Heights and Pole Bases Aren’t Shown

Mounting height affects light levels, uniformity, glare, and trespass. Many codes also cap pole height, and some measure it including the concrete base. Loudoun County, for example, measures height from grade to the top of the pole or fixture, whichever is taller.

How to fix it: Show the mounting height for every fixture in the schedule and next to each pole on the plan. Note the pole height and the base height separately (for example, “20 ft pole on 2 ft base = 22 ft mounting height”). Check that the total stays under the code limit and that the calculation uses the same number.

6. Shielding, BUG Ratings, and Color Temperature (Dark-Sky Rules)

Dark-sky style rules are increasingly common. Typical requirements:

  • Full cutoff or fully shielded fixtures, often with no light emitted above horizontal. Madison, WI requires fixtures with 500 or more initial lumens to be fully cutoff or shielded.
  • BUG ratings (Backlight, Uplight, Glare), for example U0 for uplight and a maximum glare rating. See our BUG rating guide.
  • CCT limits. Fairfax County, VA requires 3,000K or less for most outdoor lighting.
  • Total lumen limits in some codes. Ordinances based on the Model Lighting Ordinance can cap the total initial lumens for the site.

How to fix it: Add BUG rating, shielding type, and CCT columns to the fixture schedule. Choose fixtures that meet the limits, not just the light levels. Wall packs and flood lights are frequent problems because many can be tilted up. Note how they’re mounted so they can’t shine up or out. Our guide to exterior lighting for buildings covers wall-mounted fixtures. More detail is in our dark-sky compliant lighting article.

7. Light Loss Factor and Initial vs. Maintained Values Aren’t Stated

Reviewers want to know whether your values are initial (new fixtures) or maintained (after dirt and lumen depreciation). Some codes require both. Bloomington, MN asks for separate initial and maintained plans. Scottsdale sets a minimum total light loss factor of 0.70 and wants the factor shown on the plan.

How to fix it: State the light loss factor (LLF) in the schedule and say clearly which values are shown. Use maintained values to prove minimums, and initial values where the code asks for them, which is often the case for trespass and maximums. Don’t use an LLF of 1.0 just to make a plan pass.

8. The Calculation Area or Plane Is Wrong

Typical comments:

  • “Calculation does not include the drive aisles, sidewalks, or loading area.”
  • “Provide illumination along the accessible route or exit path.”
  • “Do not include light from street lights or neighboring properties.”

How to fix it: Calculate site lighting at grade unless the code says otherwise. Include every area the code regulates: parking, drive aisles, walkways from parking to the entrance, accessible routes, the exit path from building doors, loading docks, and canopies. Check egress lighting against the building code your jurisdiction has adopted. Leave out off-site lights unless the reviewer asks for them. For specific project types, see our guides to the parking lot photometric plan, the site lighting photometric plan, and the warehouse photometric plan, where loading docks and truck courts are common review items.

9. Drawing Basics Are Missing

Easy to miss, easy to fix, and still a reason for resubmittal:

  • Title block with project name, date, and revision number
  • Scale (some codes require a specific engineering scale) and north arrow
  • Property lines, buildings, parking, and walkways shown on an accurate site plan
  • Existing fixtures that will stay, not just new ones
  • Lighting controls: timers, photocells, motion sensors, and after-hours dimming if required
  • A compliance note naming the code section you’re meeting

How to fix it: Put the plan on the current civil or site plan background, add a revision date and cloud the changes, and include a short notes block that answers the reviewer’s checklist.

About seals and signatures: Some jurisdictions require the lighting plan to be signed or sealed by a licensed professional or a Lighting Certified (LC) professional. Bloomington, MN is one example. Requirements depend on the jurisdiction and the project. Stetra Lighting does not provide PE seals, so check what your reviewing authority needs before you submit.

Photometric Plan Checklist Before You Submit

Use this before the first submittal or a resubmittal:

  • Point-by-point grid over the entire site at the required spacing, to 0.1 fc
  • Grid extends past the property line as far as the code requires
  • Property line labeled, with trespass values shown (horizontal and vertical if required)
  • Calculation summary: avg, max, min, max/min, avg/min for each use area
  • Values compared to the specific code section, with a compliance note
  • Fixture schedule: tag, manufacturer, catalog number, lumens, watts, CCT, BUG rating, mounting height, LLF
  • Cut sheets attached with selected options marked
  • IES files match the exact fixtures in the schedule
  • Pole height and base height shown and under the code limit
  • Full cutoff / shielding shown for wall packs, floods, and decorative fixtures
  • Initial vs. maintained values clearly labeled
  • Parking, drive aisles, walkways, accessible routes, and exit paths included
  • Off-site lights excluded unless requested
  • Title block, date, revision, scale, and north arrow
  • Controls and hours of operation noted, if required
  • Seal or signature requirements confirmed with the jurisdiction

How to Respond to Plan Review Comments

Make the reviewer’s second look fast:

  1. Answer every comment in writing. Use a short response letter that repeats each comment and says what changed and where (sheet and note).
  2. Cloud the revisions on the drawing and update the revision date.
  3. Rerun the calculation if anything changed: a fixture, an optic, a pole location, or a mounting height.
  4. Don’t fix one comment by breaking another. Raising wattage to meet a minimum can push the property line over the limit.

FAQ

Why was my photometric plan rejected?

Most photometric plans are rejected for missing or unclear information, not bad lighting. The most common reasons are no point-by-point grid, no values at the property line, missing max/min/avg and uniformity ratios, fixture data that doesn’t match the cut sheets or IES files, and missing mounting heights or shielding details.

How many foot-candles are allowed at the property line?

It depends on the local code. Limits are often a fraction of a foot-candle, measured at the property line or a set distance past it. For example, Madison, WI allows up to 0.5 fc at 10 ft past the property line, and Loudoun County, VA allows 0.25 fc above background at the lot line. Always check your jurisdiction’s zoning or lighting ordinance.

What should a photometric plan include for plan review?

A typical plan includes a site plan with property lines, a point-by-point foot-candle grid, a calculation summary with avg, max, min, and uniformity, a fixture schedule with mounting heights and light loss factor, manufacturer cut sheets, and notes on shielding, CCT, and controls. Some jurisdictions also require vertical trespass values or separate initial and maintained plans.

Can a rejected photometric plan be revised instead of redone?

Usually, yes. Many comments only need added information, such as a summary table, mounting heights, or cut sheets. Others need a recalculation, such as new optics or shields to reduce light trespass. A full redesign is rarely needed.

Does a photometric plan need a PE stamp?

It depends on the jurisdiction and the project. Some require a licensed engineer or Lighting Certified professional to sign or seal the plan, and many don’t. Check with your reviewing authority. Stetra Lighting does not provide PE seals.

Get Your Plan Through Review

A rejected photometric plan is rarely a dead end. Most comments come down to showing the right numbers in the right place.

Stetra Lighting has prepared photometric plans for U.S. projects since 2016, with more than 1,000 projects completed. Our plans are prepared by electrical engineers using DIALux calculations, and we support plan-review corrections. Read more about our photometric plans and what a photometric plan costs.